Mount Pleasant is home to Microsoft's Fairwater AI campus, built on the land once set aside for Foxconn, with more buildings already approved. We train the electricians and technicians who build, commission and run it, at your facility or in an in-person class we set up in Racine County when you ask.
Private employers in Wisconsin are inspected by federal OSHA. Every class is live, on the 2027 edition of NFPA 70E, and taught by a Certified Safety Professional. Wisconsin electrical safety training requirements →
Among the teams we have trained in the last year
Four ways to train your Mount Pleasant crew
Crews we train in and around Mount Pleasant: data center construction and commissioning, data center operations, utility and transmission work, manufacturing in racine county, electrical and mechanical contractors, public facilities.
What the class covers for Mount Pleasant crews
On a campus that grows building by building, crews pull cable and set gear a short walk from halls already carrying load. We cover how to establish an electrically safe work condition and verify it when the source may be fed from an operating building.
AI training halls bring high-density power distribution, large UPS and battery systems, and cooling equipment that must keep running. The 2-Day Intensive covers DC systems and stored energy in depth.
Wisconsin licenses electricians statewide, but a license is not an NFPA 70E qualification. The employer still decides who is qualified for each task and documents it.
Microsoft has said it expects about 500 full-time employees at the first data center, many in critical environment roles. Newer technicians need the hazard training before they are assigned switching or maintenance tasks.
Mount Pleasant at a glance
Federal OSHA (Milwaukee Area Office)
We Energies
Statewide (DSPS)
MKE (Mitchell), ORD (O'Hare)
Central
Wisconsin: what applies to your crews
Enforcement: federal OSHA
Wisconsin has no OSHA state plan, so private employers in Mount Pleasant fall under federal OSHA through its Milwaukee Area Office. Public employers are covered separately under a state program run by the Department of Safety and Professional Services.
Licensing: statewide electrician licenses
Since April 2014 Wisconsin has required DSPS licenses for master, journeyman, industrial journeyman and residential electricians, plus registration for apprentices and beginning electricians. Electrical contractors need their own license.
Where NFPA 70E fits
NFPA 70E is a consensus standard. Employers and federal inspectors use it to show how the electrical requirements in OSHA 1910 Subpart S and 1926 Subpart K are met, and OSHA can cite the General Duty Clause for a recognized arc flash hazard.
Mount Pleasant's electrical work environment
Mount Pleasant is a Racine County village of about 28,000, roughly 30 miles south of Milwaukee and 60 miles north of Chicago. In 2017 it set aside land for a $10 billion Foxconn display plant that was never built. Microsoft took over much of that land and announced its Fairwater AI data center there in September 2025.
The first data center was confirmed operational in June 2026. A second is under construction, and the village approved 15 more buildings in January 2026. The first phase alone covers 315 acres and three buildings totaling 1.2 million square feet.
That leaves the village with two workforces on the same site. Construction and commissioning crews are still energizing new gear while operations staff run the halls that are already live.
We Energies and the Mount Pleasant load
We Energies serves Mount Pleasant. The first phase of the Microsoft campus was expected to need up to 400 MW, about 7.5 percent of the utility's maximum capacity, and Microsoft later estimated about 900 MW.
To meet that load, the Public Service Commission approved a 1,100 MW gas plant in Oak Creek and a 128 MW engine plant in Kenosha County. New substations, transmission and generation around the campus put utility-class switchgear and protective relaying in front of crews who may have spent their careers on commercial work.
Who we train in Mount Pleasant and Racine County
Electrical subcontractors, commissioning agents and GC safety staff on the Microsoft campus, where buildings come online in phases.
Critical environment technicians on UPS, switchgear, battery and cooling systems in AI halls that run continuously.
Line, substation and switching crews building the delivery capacity the campus needs.
Maintenance electricians in plants across Racine County working on drives, controls and production lines.
Southeast Wisconsin and northern Illinois contractors supplying labor to campus construction and fit-out.
Village and county water, wastewater and public works crews whose electrical systems are growing with the campus.
Also serving
Questions from Mount Pleasant employers
Do you have a scheduled class in Mount Pleasant?
Can you train our crew while they are working on the Microsoft campus?
Does Wisconsin enforce NFPA 70E?
Do you cover battery and DC hazards for data center work?
Does finishing the class make someone a qualified electrical worker?
What the people in the room say
“Virtual can never replace hands-on, but the engagement from our instructor and the class made it feel more engaging than some in-person courses I've taken.”
“Probably one of the most useful safety courses I've ever attended. Rick genuinely cares about people and their well-being.”
“This is the 2nd arc flash training course I've taken and the class was amazing. I feel like I'm leaving the training safer than before I took this class.”
Train your Mount Pleasant crew on the 2027 edition.
Onsite within a few days, or private live virtual as soon as tomorrow. Need it fast? Call (813) 725-0999.